Your annual plan probably has a date on every line. Somebody built it in a spreadsheet in October, worked out every project for the next twelve months, and gave each one a start date, an end date, and an owner. By February many of those dates are wrong, and everyone knows it, but the plan still gets reviewed as if they weren’t. The Now, Next, Later roadmap was built to stop exactly that.
A dated annual plan is waterfall planning, and most businesses still do it outside the product team. Where I work, we stopped. The whole business now plans with it, product and every other team alike.
Three columns and no dates
I saw the idea announced when I was working in Brighton. I have always paid attention to new things arriving in my trade, and this one came from people local to me, so it was a double whammy. Janna Bastow tells the story on ProdPad: her team’s plans lived in tools that were almost impossible for anyone outside the team to read, and she wanted something a stakeholder could understand in about ten seconds, without pretending I knew the exact week any of it would ship. In her words: So I dropped the dates and drew three columns: Now, Next, and Later. In a reply to readers she adds that the first version, sketched with her co-founder Simon Cast in 2012, was called Current / Near Term / Future.
The format spread through product teams because it removed a lie. A timeline roadmap presents a guess as a commitment. Now, Next, Later says only what you are doing, what is probably coming, and what you know you will have to deal with eventually.
Each column is a level of certainty
What makes it work beyond product is that each column is a statement of how sure you are:
- Now is committed: staffed, scoped, and happening.
- Next is probable: you expect to do it, but the detail is still moving. Bastow says it is broken down less finely, with fewer specifics and details.
- Later is a set of problems you know about, not solutions you have chosen. Her phrase is big boulder blocks that are still hazy, and her rule is prioritize problems, not ideas.
Every team plans under uncertainty, and few plans admit it. Finance, marketing, operations, and people teams all have the same three kinds of work: what they are doing, what they expect to do, and what they know is coming but can’t shape yet. A dated plan flattens those into one list and gives them all the same false precision. The three columns keep the difference visible.
The project model has a second problem that the columns help with. It measures dates met and projects delivered, not outcomes, so nobody can tell which projects earned their keep: the measurement debt I described in Which Product Manager Is AI Replacing? A plan built around problems in Later invites the question of whether the work in Now solved them.
Leadership still asks for dates
It doesn’t go smoothly. Leadership still asks for dates, and it asks for certainty about things in Next and Later. That is a fair instinct: dates feel like accountability, and a board wants to know when.
Our answer is one rule: we talk dates for what is in Now. If someone needs a firm date or a firm commitment for something in Later, that is a signal it should not be in Later. It belongs in Now, and something currently in Now has to make room for it. Asking for certainty about a card is asking to move the card, and moving it has a cost that everyone can see.
That conversation is far more useful than a negotiated date. It turns when will it be ready? into what do we stop to make it ready?, which is the question the business should have been asking anyway. Bastow warns that a horizon with no shared definition just becomes a vaguer timeline, and this rule is what keeps the horizons from sliding back into one.
Dates that are real
Some dates are not guesses. The financial year closes when it closes, a contract renews on a fixed day, and a regulator sets its own deadlines. Those go on the plan as constraints on a card: Now: contract renewal, due 31 March. What leaves the plan are the invented dates, the ones guessed months ahead for work nobody has scoped yet.
The approach puts commitment where you have the information to make it, in Now, and stops you making it in Later, where you don’t. It also makes the plan easier to change, which matters more each year: when building gets faster, as it has with AI, a plan dated twelve months ahead goes stale sooner.
Taking it beyond product
If you want to try it outside product, a few things make the difference:
- Agree what each column means before anyone fills it in. Now might mean this quarter, committed and staffed.
- Write Later as problems, not projects.
- Put fixed deadlines on the card as constraints, never as the shape of the plan.
- Review on a fixed rhythm and move cards left as certainty grows.
I wrote about treating the company itself as something you design in Company as a Product You Never Managed. Planning is part of that design, and most companies inherited theirs from a project-management template nobody chose.
A plan doesn’t need dates to be serious. It needs to say what you know, what you think, and what you’re only guessing.